CCCSD strives to ensure that our collection and treatment systems operate in the most efficient manner possible. Through an aggressive capital improvement plan, we initiate projects to upgrade our infrastructure and utilize the most advanced, cost-effective equipment and processes available. As these projects develop, we'll keep you informed about them through this section of our site.

Alhambra Valley Trunk Sewer Project


Point of Contact: Chris Carpenter, (925) 229-7316

Project Description:
The District will be constructing a gravity trunk sewer to serve the Alhambra Valley, south of the City of Martinez. The trunk sewer will extend from Gilbert Lane south to the Alhambra Valley Road/Reliez Valley Road intersection about a mile away. Properties directly along the trunk sewer route will be allowed to connect houses directly to the trunk sewer. Properties not immediately adjacent to the trunk sewer may need to construct a public main sewer to reach the trunk sewer. See the October 2005 project mailing which contains more information and a map of where additional public main sewers may be needed. Construction is planned to occur in two phases; Phase I in Summer 2006 and Phase II in Spring/Summer 2007. Estimated construction cost: $4 million.

Updates:

October 8, 2007 Construction has begun on Phase 2 of the Alhambra Valley Trunk Sewer Project.  Work on this final phase, which involves Wanda Way and the National Park Service property across the creek at Strentzel Lane, is expected to be completed by early January 2008.  If you have questions about this construction, please contact Chris Carpenter at 925-229-7316.  Annexation of 242 Alhambra Valley properties to CCCSD's service area will be on the November 14 agenda of the Contra Costa Local Agency Formation Commission.  Also in November, CCCSD plans to begin initiating formation of voluntary assessment district to finance direct and indirect connections to the trunk sewer and needed main extensions.

June 29, 2007 A draft Negative Delclatrtion has been prepared for annexation of 242 Alhambra Valley properties to CCCSD's service area. The public review period is June 29, through July 30, 2007. For more information see the Notice of Intent to Adopt a Negative Declaration.

June 1, 2007: A status report PDF icon to Alhambra Valley residents regarding trunk sewer construction, National Park Service right-of-way, annexation, and the financing program is available.

November 2, 2006: The District Board gave final approval to an Alhambra Valley Sewer Financing Policy.  The staff report and Board presentation  contain the details of the financing policy and an update of project costs.

August 3, 2006: The District Board approved the concept of an Alhambra Valley Sewer Financing Program.  The handout from that meeting describes staff's general recommendations for the program.  More details will be developed and presented for Board consideration later this year.


Lafayette Sewer Renovation Project, Phase 5


Point of Contact: Chris Carpenter, (925) 229-7200

Project Description:
This project is the fifth phase of a renovation program to replace deteriorating sewers in Lafayette.  This project will replace existing 6-inch sewers at 10 different Sites. Approximately 10,000 feet of sewer will be renovated using the pipe bursting method. Several sites involve work on private property easements.

Construction Schedule: July 2008 – December 2008


Walnut Creek Sewer Renovation Project, Phase 6


Point of Contact: Chris Carpenter, (925) 229-7200

Project Description:
This project is the sixth phase of a renovation program to replace deteriorating sewers in residential areas of Walnut Creek.  The project will replace existing six and eight inch sewers at seven separate sites. Approximately 10,000 feet of sewer will be renovated using open cut and pipe bursting methods. Several sites involve work on private property easements.

Construction Schedule: June 2008 – November 2008